| Date | Progress | Pictures | ||||||||||||
| 26th January 2007 | Went to notary with Sam from Pedro's office to prove we agreed with the legalisation. As we climbed up the motorway from Murcia the snow started to lie at Mula, and the low cloud covered Bullas. Met with Phil, Ena and Gines to review extra work. |
|
||||||||||||
| 23rd January 2007 | Got the keys for the gates and went over to inspect. Extra terracing and all grills complete - looked good. |
|
||||||||||||
| 15th January 2007 977 days |
We now own the house. Paco has been paid in full and the house has been legalised. Now Gines can get on with the side arches. |
|
||||||||||||
| 3rd January 2007 965 days |
Yesterday Phil and Ena visited the house with Gonzalo and checked Snag List. Most of the things on it have been completed. We have asked Pedro to go ahead with legalising the house and paying Paco the remaining money less 2,000 Euros to cover connecting the water. Pedro thinks he can complete that next week. |
|
||||||||||||
| 13th December 2006 944 days |
Phil and Ena went back to look at the work Gines has completed - they suggested some more tiling around the pool. |
|
||||||||||||
| 5th December 2006 936 days |
Phil and Ena rang after a two week holiday. They visited the house and Gines has completed the retaining wall and steps. There was a painter in the house. |
|
||||||||||||
| 4th December 2006 935 days |
Got a phone call from Gonzalo that he has at last got the licence. |
|
||||||||||||
| 13th October 2006 883 days |
Back to the site, we met a salesman for solar water heating, who can supply a system to provide hot water and central heating. He will give us a quote - see SolarDirecta for details. Went to Caravaca to see Gonzalo and at last got a key for the gate so that Gines ( our other builder ) can get in. Told Gonzalo that is all is not completed by end of 2006 we will break the contract with Paco and find another builder. |
|
||||||||||||
| 11th October 2006 881 days |
Met at the house with Phil, Ena and their builder Gines to agree other building work
we would like to be completed as soon as possible, some of which will only be possible once we own the house.
|
|
||||||||||||
| 10th October 2006 880 days |
Met Gonzalo at the house and went through the Snag List - some had been complete but quite a bit still to do. No sign of the paperwork yet from the town hall, but it is supposed to be all agreed. |
|
||||||||||||
| 23rd June 2006 771 days |
We visited the house and the plumber was in fitting the bidets. Apart from the kitchen items like sink, hob and extracter nothing else has been finished. |
|
||||||||||||
| 8th May 2006 725 days |
Phil and Ena visited and could see that the kitchen had been finished, but could not get in due to lack of the key. |
|
||||||||||||
| 13th April 2006 700 days |
Gonzalo could not come to meet Phil and Ena, but they visited and could see that some work has been done. |
|
||||||||||||
| 7th April 2006 694 days |
Met Ena, Gonzalo and his foreman, Manuelo, at the house. Gonzalo has ordered a number of the missing items ( boiler, bidets ) and work will start tomorrow ! Ena will visit the site again with Gonzalo on Wednesday before Semana Santa to check progress. Gonzalo also reported that the architect has found out that the paperwork will be ready in 4 weeks. |
|
||||||||||||
| 3rd April 2006 690 days |
Met Gonzalo at the house with Phil and Ena. He explained that there was a large backlog of paperwork in Murcia, with the possibility that our approval might not be through until September. We said we wanted the work finished as soon as possible and went round the house to produce a snags list. |
|
||||||||||||
| 31st March 2006 687 days |
Met Phil and Ena at the house but no Gonzalo ! No work has been done on the house since the last visit. Bought table and chairs and gazebo from Phil and Ena's shop. Sent e-mail to Gonzalo saying we wanted to see some progress or we would find another builder. |
|
||||||||||||
| 2nd March 2006 658 days |
Phil managed to visit the house. The carpenter has fitted the kitchen units but no worktop. The fitted wardrobe doors are fitted and bathrooms fitted. There are three damp patches from the solarium - Phil has sent a snag list to Gonzalo. No news on the paperwork from the town hall. The approach road has been improved. |
|
||||||||||||
| 24th November 2005 560 days |
Met with Gonzalo, Philip and Ena. The carpenter will visit soon to measure up the kitchen, the internal doors and bathroom units are arriving in the next two days. The painter has almost finished, but we spotted a wet patch in the main bedroom. The hole for the septic tank needs to be larger and a machine is coming to dig it soon. The local council are due to inspect the the completed house at the end of January 2006. |
|
||||||||||||
| 23rd November 2005 559 days |
We visited the site but no workmen. The fencing is complete, the pool surround tiled, the wardrobes built, a TV arial fitted but no kitchen or bathroom fittings |
|
||||||||||||
| 26th October 2005 531 days |
Philip and Ena visited. The changing room / pump room has now been completed. The holes / trenches for the drains / septic tank have been dug out. There were no builders on site so Phil could not get into the house but he could see that they have started one of the wardrobes. |
|
||||||||||||
| 14th October 2005 519 days |
Philip and Ena visited. The arches have now been completed and the shell of the changing room / pump house in almost complete. |
|
||||||||||||
| 7th October 2005 512 days |
We visited the site to look at the progress. The arches had been finished but not plastered / painted. They had filled the area around the pool and filled the pool with water. The foundations of the changing room / pump house were being laid. |
|
||||||||||||
| 28th September 2005 503 days |
We met Paco and Gonzalo at the site with Phil and Ena. We arches had been started and all the windows were glazed. They were plastering the ceilings in the bedrooms and corridor. The doorways into the two end bedrooms had been completed. The pool has been tiled and finished off, but the area around it not filled in. The changing room could not be in the place we wanted, but would need to be in the corner of the terrace beyond the pool. |
|
||||||||||||
| 5th September 2005 480 days |
Philip and Ena went to inspect the pool. It is 8m x 4m instead of the 10m x 5m we ordered. They say that they could not fit in a larger pool - but they could have easily added an extra metre to the length. |
|
||||||||||||
| 25th August 2005 469 days |
Philip heard that new builders were going to start, replacing Vladimir, soon. The pool company started today, but there was some confusion about the size of the pool and whether the plot is large enough for a width of 5 metres. | |||||||||||||
| 24th June 2005 407 days |
We met Paco with Philip and Ena at the site. No work has been done for the last month because Vladimir the builder has injured his ankle falling on the site. He will probably be off for another three weeks. We told Paco that we wanted the house and everything finished by the end of September. We would wait for the building permit if it was not ready then. |
|
||||||||||||
| 24th May 2005 376 days |
Philip and Ena visited but the doors were locked - so they could only take photos through the glassless doors. |
|
||||||||||||
| 4th May 2005 356 days |
Work started on the fireplace. |
|
||||||||||||
| 25th April 2005 347 days |
We visited the lawyer, Pedro, near Torrevieja. He has 6 other clients all in the same situation waiting for Paco to finish their houses. He is trying to get a schedule for completion for all the houses. He thinks, based on past experience, the house will not be completed with the correct paperwork from the town hall until September (2005 !). | |||||||||||||
| 22nd April 2005 344 days |
The external doors have all been fitted - internal ones still missing. Sealing and colouring the outside walls in yellow above the waistline is complete, below the waistline in red has started. |
|
||||||||||||
| 13th April 2005 335 days |
Outside tiling is now complete. The doors have arrived to be fitted. Sealing and colouring the outside walls has started. |
|
||||||||||||
| 6th April 2005 328 days |
There have been more tiles laid on the path round the perimeter and working on tiling stairs to solarium . Rendering around windows is complete. Floor tiling completed and wall tiling completed except for small area at side of kitchen door. Plastering completed. Position of breakfast bar moved. |
|
||||||||||||
| 31st March 2005 322 days |
Some outside tiling done, bathrooms ready for suites, lounge / kitchen being plastered. Breakfast bar still in wrong place, but they know about it !. |
|
||||||||||||
| 28th March 2005 319 days |
The solarium has been tiled - so hopefully no more rain into the bedroom area. Despite a number of phone calls and a map from Phil they had started the breakfast bar in the wrong place - Pablo is sorting that out. | ![]() |
||||||||||||
| 15th March 2005 306 days |
Philip visited, no men on site but there were tools so they cannot have been far - next job is to seal the roof of the bedroom area - under solarium. |
|
||||||||||||
| 9th March 2005 300 days |
Phil visited but the walls still need to dry out. | |||||||||||||
| 2nd March 2005 293 days |
Phil visited the site after 24 hours of snow ! The walls have been plastered and the floors tiled but it needs some dry weather for the inside of the house to dry out. | |||||||||||||
| 21st February 2005 284 days |
As it was raining on the coast we went back to Cehegin, walked up into the old town and spotted our new house in the distance ( picture out of focus ! ) - also had a look at a similar one to check we still liked the colours ! Four men on site now, two preparing walls for plastering and two laying tiles in the bedroom. |
|
||||||||||||
| 18th February 2005 281 days |
Phil rang on the day we arrived in Spain to say that work had started. Visited the site and two workmen had started to plaster walls after fitting the windows. The tiles had arrived. |
|
||||||||||||
| 11th February 2005 274 days |
Phil spoke to Paco earlier in the the week and was told that a new builder would be starting on Wednesday - however when Phil visited the site on Friday no progress since 30th November. | |||||||||||||
| 28th January 2005 260 days |
Phil reports the first snow in the area in 50 years - so too cold to lay tiles ! A picture from the side of Phil and Ena's house. | ![]() |
||||||||||||
| 21st January 2005 253 days |
Paco decided that he needed to bring forward our next payment ( which should have been paid on completion of the house ) so that he could continue to pay the workers ! He also thought we needed to pick some more floor tiles as our chosen design had been discontinued. After Phil and Ena found that there was no problem with the tiles, Pedro agree that we could pay the next instalment early - so that was transfered today. Paco says the house will be complete in one month ! | |||||||||||||
| 30th December 2004 231 days |
After they returned from UK, Phil and Ena visited the site and there has been no work done in the last month ! It certainly wasn't finished. They will chase Paco to find out what is happening and we sent an email to Pedro to also chase them up. | |||||||||||||
| 20th December 2004 221 days |
John from the builders office e-mailed us to say that the bathroom tiles we choose in July were not made any more so we choose alternative ones. | |||||||||||||
| 3rd December 2004 204 days |
Days after Phil and Ena left Spain, Paco phoned our lawyer, Pedro, to say that the house was finished and that they wanted the next staged payments. We could not believe them, three days ago there were no windows in the building - we sent Paco a list of things we expected to be finished. | |||||||||||||
| 30th November 2004 201 days |
Phil and Ena visited the site just before setting off for their Christmas break to UK and Cuba. The floors had been screeded, covering the pipes and cables. | |||||||||||||
| 19th November 2004 190 days |
The roof is now tiled with the chimney built. Electrical work and plumbing now almost complete. The charging room/pump house will now need to go next to the main bedroom. We went to Caravaca to confirm our choose of kitchen cabinets and worktops. |
|
||||||||||||
| 10th November 2004 181 days |
The structure is now almost complete, all window openings in and electrical work inside has started. |
|
||||||||||||
| 3rd November 2004 174 days |
Getting on with the roof, the doorway into the storeroom is in. |
|
||||||||||||
| 27th October 2004 167 days |
The windows are now in the correct positions. The front patio pillars and roof are being build, along with the ceiling over the kitchen / dining area. |
|
||||||||||||
| 19th October 2004 159 days |
Most of the walls are now up to first floor height. Two of the windows are in the wrong place and the bedroom patio wall is too large. Philip is contacting the builders to ensure that the changes are made. |
|
||||||||||||
| 8th October 2004 148 days |
Concrete slab has now been poured and the bricks delivered |
|
||||||||||||
| 1st October 2004 141 days |
Following summer holidays, a
change in building contractor and a two week Cehegin Fiesta - the
builders have pegged out the plot, dug out the foundations and pool
and filled the foundations with chippings ready for the
concrete. To see more pictures from the visit click here |
|
||||||||||||
| 30th July 2004 78 days |
Phil and Ena visited the site.
The building area has now been levelled. To see more pictures of the building site click here |
|
||||||||||||
| 14th July 2004 62 days |
Visited the site again, the
irrigation channel has now been crossed with a pipe covered with
concrete - opening the way to the building area. Walked over the site more - plenty of fig trees, pomegranates, olives, almonds and vines. Then we went to the show house to try to imagine the finished article ! |
|
||||||||||||
| 8th July 2004 56 days |
Visited a furniture shop in Pilar de la Horadada used by Philip and Ena in the past. Ordered furniture for the lounge and 3 bedrooms to be delivered once the house is built. | |||||||||||||
| 6th July 2004 54 days |
A quick visit to the plot in Cehegin, to see no further work - held up by a irrigation channel blocking the way down to the building area. Then on to Caravaca with Philip and Ena to choose tiles for floor, terrace, bathrooms and kitchen, then to the kitchen shop to choose doors and worktop. | |||||||||||||
| 23rd June 2004 41 days |
Water is now connected to the
site and the bulldozer has opened the entrance to the plot from the
road and levelled a track down to the building area. Work has been delayed while the town hall in Cehegin agreed the plans. |
|
||||||||||||
| 13th May 2004 | Plot purchased and contract signed with the builder to complete the construction in 120 days | ![]() |